Vulcan Res 03 March and 10 March

Posted: Thu Feb 14, 2019 10:40 am
by MerlinL14
It is proposed to hold 2 Sunday work parties on Vulcan Res (3 and 10 March). There are 8? pegs that are in need of renovation, 2 were done late last year as a 'test' to gauge the manpower and resources required.
Work schedule for the peg renovation: The diamond plate will be removed, the wood structure removed/disassembled, scaffolding poles made secure, new wood planks installed and the diamond plate reinstalled. We achieved this with 3-4 people on each peg in less than an hour per peg. The more that turn up the more we can achieve on each day of the work party.
The Res will be closed to fishing on both these Sundays, if we do not achieve the peg renovation on these 2 Sundays then the Res will be closed on further days so this vital work can be carried out.
This is the only major work required on this water and getting it done this early in the year will negate the chances of further closures as grass cutting and tree pruning can be carried out without closing the water.
If you are turning up then you will not require any tools, other than cordless drill/screwdriver, hammer if you have these.
Please bring work gloves

Re: Vulcan Res 03 March and 10 March

Posted: Tue Feb 26, 2019 1:53 pm
by MerlinL14
10:00 AM start.